Project Failure – Channel Tunnel

The Channel Tunnel Rail Link source: Akanekal (via Flickr)

The Channel Tunnel or Chunnel is a 31  mile tunnel running underneath the English Channel to carry Eurostar trains and freight trains between the UK and France.

Construction of the tunnel started in 1988, the project took approximately 20% longer than planned (at 6 years vs. 5 years) and came in 80% overbudget (at 4.6 billion pounds vs. a 2.6 billion pound forecast).

The tunnel wasn’t completely unprecedented. The Seikan Tunnel in Japan had similar length and depth. Nonetheless, like projects such as NASA’s missions and the Sydney Opera House, it seems part of the reason for cost overrun was the absence of many precedents and associated experience to base sound estimates off. In fact, subsequently, the Channel Tunnel has been listed as one of the engineering wonders of the world, which emphasizes its uniqueness.

The issues that caused delay resulted from three factors:

  • Changed specifications for the tunnel, there was need for air conditioning systems to improve safety that were not included the initial design.
  • The communication between the British and French teams who were essentially tunneling from the two different sides and meeting in the middle could have been improved. Theses sorts of communication issues are relatively common in delayed projects when tensions rise, Wembley Stadium is an interesting example, where poor communication meant that junior employees where often more informed about project status than senior managers.
  • The contract was bid on by competing firms, this framework will necessarily encourage the ‘winner’s curse’ of the successful bidders having the lowest and most optimistic price estimates, again the Wembley Stadium project offers another example of the winner’s curse.

Another interesting aspect of the Channel Tunnel’s forecasts were that a lot of revenue was projected to come from driving the existing ferry operators out of business. Of course, these ferry operators were the main way to cross the English Channel before the Channel Tunnel existed. However, this analysis ignored the possibility that the ferries would react to the Channel Tunnel with improved pricing and service, leading to them retaining market share. In addition the creation of budget airlines providing cheap air travel between UK and France was not foreseen. It is a good reminder that in making strategic forecasts of benefits or results you should bear in mind how competitors will react to the project you are envisioning.

Whilst it is not a project management issue per se, it should be noted that a great deal of the financial problems with the Channel Tunnel were caused by overly optimistic revenue projections, on top of the construction cost overruns, and those projections failed to anticipate that the set of options for getting from Paris to London might change, both in reaction to the tunnel and because of innovation in other areas such as the development of the budget airline business model.

See more project management case studies at www.projectcasestudies.com or follow me on Twitter for blog updates.

Channel Tunnel Drilling Equipment (source: Tony Bradbury)

2 responses to “Project Failure – Channel Tunnel

  1. Pingback: A strong UK economy is pushing more passengers out, and pulling more freight in, through the Channel Tunnel – Quartz

  2. What were the procurement problems in the eurotunnel project and how could they be overcome?

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s